We are a leading design office specializing in closed cooling circuits installed in power station units, which include natural and mechanical draft cooling towers. Below you will find the list of our projects. We prepared construction and executive project of a 134 meters high cooling tower for the new power unit in Lagisza Power Station.

Realisations

 Year  Subject Localisation Photos
2013 Construction project of cooling tower in Legnica. Legnica Power Plant
2013 Executive project of forced-draught cooling tower in Janikowo. CHP Janikowo
2012 Geometric imperfections of the shell cooling tower no. 2 in ERSA. Rybnik Power Plant
2012 Executive project of reinforced concrete hyperboloid shell enhancement of cooling tower no. W-2/6 in Belchatow Power Plant S.A. Belchatow Power Plant
2011 Executive project. Reinforcement of the cooling tower W-2/5 in Belchatow Power Plant Belchatow Power Plant
2010 Risks assessment of the cooling tower no. 1 in ERSA. Rybnik Power Plant
2012 Construction project of forced-draught cooling tower of upper circuit PZ i PF/ MODERNIZATION PROGRAM OF PIROMETALLURGY IN KGHM KGHM
2010 Executive project of forced-draught cooling tower chamber no. 4 of circuit FKS I modernization in HM Glogow. HM Glogow
2008 Static and strength calculations of desulphurized flue gas ducts for the cooling tower H=178m in Belchatow II Power Plant. Belchatow Power Plant
2007 Project the cooling tower in Łagisza Power Station Lagisza Power Station gallery
2006 Construction project, Executive projects, static calculations and dimensioning of the cooling tower H=133m Lagisza Power Plant.
2006 Constructional Project. Silencing the cooling tower no. 1 in Heat and Power Plant 2 in Lodz Power Plant Lodz
2006 Executive Project. Modernization of 3 cell forced cooling tower with mass flow 1000m3/h in Mahle Poland in Krotoszyn Mahle Krotoszyn
2006 Executive Project. Modernization of forced cooling tower in Heat and Power Plant 4 in Lodz Power Plant Lodz gallery
2005 Concept of development of the cooling system in Heat and Power Plant Zofiowka Power Plant Zofiowka
2005 Executive Project. Modernization of cooling tower H=40m in PCC Rokita Plc PCC Rokita Brzeg Dolny
2005 Executive Project. Modernization of cooling tower in Rybnik Power Plant Rybnik Power Plant
2004 Executive Project. Modernization of forced cooling tower in Refiner Trzebinia Refiner Trzebinia gallery
2004 Executive Project. Modernization of inner instruments in cooling tower no 2 in Heat and Power Plant Moszczenica Power Plant Moszczenica
2004 Executive Project. Modernization of cooling tower in Unilewer Katowice Unilewer Katowice gallery
2004 Executive Project. Modernization of cooling tower no. 1 in Power plant Rybnik Rybnik Power Plant
2004 Executive Project. Modernization of cooling tower no. 2 in Power plant Rybnik Rybnik Power Plant
2003 Executive Project. Modernization of 2 cell forced cooling tower with fans ø 8m and mass flow 5800m3/h in Heat and Power plant Swiecie Power Plant Swiecie
2003 Review and evaluation of technical condition of fill pack, piping, drift eliminator and prefabricated construction of inner instruments in cooling tower no.2 in Power plant Rybnik Rybnik Power Plant
2003 Concept of limiting noise emission from cooling tower no.1 H=120m in Power plant Rybnik Rybnik Power Plant
2002 Executive Project. 2 cell forced cooling tower with fans ø 4m and mass flow 1000m3/h – unit 700 for Hydrokomplex Glimar in Gorlice Glimar Gorlice
2002 Executive Project. of 2 cell forced cooling tower with fans ø 7m and mass flow 7100m3/h in Pulawy Plc ZA Pulawy S.A. gallery
2002 Executive Project. Draining pipeline from 4 cell forced cooling tower with fans ø 6m for Zaklady Chemiczne Zachem in Bydgoszcz Zachem Bydgoszcz
2001 Executive Project. 2 cell forced cooling tower with fans ø 7.1m and mass flow 4690m3/h in Heat and Power Plant RZESZOW Power Plant Rzeszow
2001 Executive Project. 3 cell forced cooling tower with fans ø 7.1m and mass flow 5000m3/h in Heat and Power Plant BIALYSTOK Power Plant Bialystok
2001 Technical Project. 4 cell forced cooling tower with fans ø 2 and mass flow 331m3/h on installation of ethylene oxide and poly ethylene glycol – PKN Orlen, Plock PKN Orlen Plock
2001 Project of platform of 2 cell forced cooling tower with fans ø 6.2m and pipeline with cooling water in Heat and Power Plant Knurow Power Plant Knurow
2001 Executive Project. 2 cell forced cooling tower with fans ø 6m and mass flow 3000m3/h – unit 700 at CHP Gorlice CHP Gorlice
2001 Renovation of 2 cell forced cooling tower with fans ø 5m in TIMKEN Sosnowiec TIMKEN Sosnowiec
2001 Renovation of 1-4 cooling tower’s steel construction in Power Plant Halemba Power Plant Halemba
2000 Renovation of no. 1 cooling tower’s hyperbolical reinforced concrete surface in Power Plant Rybnik. Review, description, technical condition Rybnik Power Plant
1999 Review and assessment of no. 2 cooling tower’s hyperbolical reinforced concrete surface in Copper Works in Glogow Glogow Copper Smelter
1998 Review and assessment of technical condition and concept of renovation of no. 2 cooling tower’s surface in Power Plant Rybnik Rybnik Power Plant
1995 Assessment of safety of no. 1 cooling tower’s surface in Power Plant Jaworzno III taking irregular deplacement and geometric imperfections. Rybnik Power Plant

Other realisations