Structural engineeringWe prepare engineering specification of steel constructions together with three-dimensional models. The reinforced concrete structures are designed by engineers who have access to the best software available on the market.
Realisations
Year | Subject | Localisation | Photos |
---|---|---|---|
2013 | Construction project of inclined conveyor bridge PT-4 in ZW Tychy | ZW Tychy | – |
2012 | Modernisation of push-plate conveyor for the ash transport 8/1RNZ at the 8IOS in ERSA | Rybnik Power Plant | – |
2012 | Executive Project of cargo and passenger lift assembly at the level +8,50m at the power unit 4 in ERSA | Rybnik Power Plant | – |
2012 | Pillars reinforcement of the ash container supporting structure V=400m3 in Konin Power Plant | Konin Power Plant | – |
2011 | Executive project. Adaptation boiler staircases according to current firefighting requirements and preparing of assumption far a carburizing gallery doors replacement in Rybnik Power Plant. | Rybnik Power Plant | – |
2011 | Visualization of new 900MW power supply unit in EDF Rybnik S.A. | Rybnik Power Plant | gallery |
2011 | Executive project of steel ash tank V=400 m3. | Rybnik Power Plant | – |
2010 | The concept of existing support structure enhancement of absorber flue gas ducts IOS of block no. 8 in PGE Power Plant Belchatow S.A. The aim of this study is to determine the necessary scope of supporting structure and foundations reinforcement for a enabling installation of heat exchangers. Heat exchangers are is installed on the inlet and outlet channels of the absorber of IOS block no. 8 | Belchatow Power Plant | – |
2010 | Inspection and technical condition assessment of chamber ash tank of II part in Rybnik Power Plant. | Rybnik Power Station | – |
2010 | Executive project of new heat station D3 building piling in Belchatow Power Plant | Belchatow Power Plant | – |
2010 | Construction project of biomass silos in Jaworzno III Power Plant II. | Jaworzno Power Plant | – |
2010 | Executive project – supporting structure of flue gas ducts for the CCS in Belchatow Power Plant. | Belchatow Power Plant | – |
2010 | Construction and executive project of transport, storage and processing instalation in the CHP Kraków. Part 1- Storage management of biomass | CHP Krakow | – |
2010 | Construction and executive project of transport, storage and processing instalation in the CHP Kraków. Part 2 – Grinding and pneumatic transport of ground biomass | CHP Krakow | – |
2009 | Construction and executive project of railway siding and internal access roads in Rybnik Power Plant for the construction needs of the new 900 MW power unit. | Rybnik Power Plant | – |
2009 | Construction and executive project of biomass feeding system excluding coal pulverizers of boilers 1-4 in Rybnik Power Plant. | Rybnik Power Plant | – |
2009 | Construction and executive project of repair house of glass-making machines for the O-I Polska in Jarosław. | O-I Jaroslaw | – |
2009 | Analysis of foundation conditions for the 900MW power unit facilities in Rybnik Power Plant, after a preliminary study of the ground. | Rybnik Power Plant | – |
2008 | Construction and executive project of the road tankers unloading station improvement. Industrial use of fly ashes installation – the main plant KWK Chwałowice | KWK Chwalowice | – |
2008 | Construction project of the hazardous materials warehouse in Rybnik Power Station | Rybnik Power Plant | – |
2003 | Executive Project. Exchange and silencing of housing of the central Pumping Station in Rybnik Power Plant – stage 2. | Rybnik Power Plant | – |
2002 | Execution Project. Repair of the facade of an output shaft no. 1 in Pniowek Coal Mine. | KWK Pniowek | – |
2002 | Constructional Project. Ash holding container with capacity of 600m³ in Chwalowice Coal Mine KWK | KWK Chwalowice | – |
2002 | Executive Project. Spray drying room. | – | |
2002 | Executive Project. Renovation of steel retaining construction of ash holding container with capacity of 4x2000m³ in Rybnik Power Plant | Rybnik Power Plant | – |
2001 | Acoustic wall insulation in the engine room in Rybnik Power Plant | Rybnik Power Plant | – |
2001 | Supporting construction of areals and relay station for cell telephony network in Rudniki Cement Mill | Rudniki Cement Mill | – |
2001 | Constructional and Executive Project. Coal storing site in Debiensko Heat and Power Plant | Debiensko Heat and Power Plant | – |
2001 | Executive Project. Exchange and silencing of housing of the central Pumping Station in Rybnik Power Plant – stage 1. | Rybnik Power Plant | – |
2001 | Constructional Project. Technical gases warehouse. | – | |
2001 | Evaluation of technical condition and preparation of renovation project of coke extinguishing tower no. 3 in ZK Zdzieszowice | ZK Zdzieszowice | – |
2000 | Constructional and Executive Project. System of boiler coaling in Dębieńsko PE “MEGAWAT” – Plant Z 1 | PE Megawat | – |
1999 | Constructional and Executive Project. Tennis hall for „Energetyk” Club in Rybnik | Rybnik Power Plant | – |
1998 | Technical Project. Foundation of supporting construction of calcium container and maintenance platform around it located above the track no. 43 in Rybnik Power Plant | Rybnik Power Plant | – |
1998 | IInstallation of calcium transportation system in container V=500m3 in Rybnik Power Plant. Bearers and overpass posts | Rybnik Power Plant | – |
1997 | Technical Project. Reinforcement of ash container located in dispatch station of unit 8 in Rybnik Power Plant | Rybnik Power Plant | – |
1997 | Technical Project of subgrade construction crane SS1 reconstruction at the 1st stage wastewater treatment plant | Rybnik Power Plant | – |
1997 | Executive Project. Modernization of flue block casing in units no. 1 and 2 in Rybnik Power Plant | Rybnik Power Plant | – |
1997 | Constructional Project. Parking lot for passenger cars, a new reception and car scales in the area of an inner road in Rybnik Power Plant | Rybnik Power Plant | – |
1997 | Technological Project. Platforms of measuring spots installed on hot air pipe of flue gas desulphurization system in unit 1 in Rybnik Power Plant | Rybnik Power Plant | – |
1997 | Technological Project. Bearing construction of cable line in the area of flue gas desulphurization system in unit 1 in Rybnik Power Plant | Rybnik Power Plant | – |
1997 | Sealing of the walls of a water settler in Water Treatment Plant in Stodoly, Rybnik | Rybnik Power Plant | – |
1995 | Steel construction of boiler for Nettgau Span (Germany) | Nettgau Span | – |